METHOD OF PROTECTING METAL AND PLASTIC PIPE IN FEF INSULATION PENETRATING A RIGID WALL ACCORDING TO ETA-17/1063

1.png

1 - rigid wall thickness B = min. 100 mm
2 - plastic pipe, diameter "D" and wall thickness "t"
3 - the space between the pipe insulation and the wall structure in
     width u = max. 15 mm, filled with gypsum plaster to the depth min. 10 mm
4 - Piro Collar PC mounted on both sides of the wall
5 - fire collar mounting - steel expansion anchor bolt M6x60 or M8x80

Technical drawing
Carbo Collar Rury Metalowe w kauczuku ściana sztywna 1.png

Fill the space between the pipe insulation and the partition tightly. Use cement mortar.

Steps 1 - 5

Place the collar on the pipe insulation. In case of collars with a diameter of PC-125 and larger L, first wrap the pipe four times with an intumescent insert and then put the steel cover on top.

Carbo Collar Rury Metalowe w kauczuku ściana sztywna 2.png
Carbo Collar Rury Metalowe w kauczuku ściana sztywna 3.png

Pull the locking pin of the clamp through the fixing slot on the other end of the collar and fold it 180° backwards so that the collar is firmly closed on the pipe.

Attach fire collar to the wall with expansion anchor bolts. Do not use expansion anchor bolts containing plastic elements.

Carbo Collar Rury Metalowe w kauczuku ściana sztywna 4.png
Carbo Collar Rury Metalowe w kauczuku ściana sztywna 5.png

Mark the completed penetration seal with the label attached to the set. Mark Piro Collar PC on it, enter the date and the name.

Carbo Collar Rury Palne w kauczuku ściana sztywna 1.png

Fill the space between the pipe insulation and the partition tightly. Use cement mortar.

Steps 1 - 5

Place the collar on the pipe insulation. In case of collars with a diameter of PC-125 and larger L, first wrap the pipe four times with an intumescent insert and then put the steel cover on top.

Carbo Collar Rury Palne w kauczuku ściana sztywna 2.png
Carbo Collar Rury Palne w kauczuku ściana sztywna 3.png

Pull the locking pin of the clamp through the fixing slot on the other end of the collar and fold it 180° backwards so that the collar is firmly closed on the pipe.

Attach fire collar to the wall with expansion anchor bolts. Do not use expansion anchor bolts containing plastic elements.

Carbo Collar Rury Palne w kauczuku ściana sztywna 4.png
Carbo Collar Rury Palne w kauczuku ściana sztywna 5.png

Mark the completed penetration seal with the label attached to the set. Mark Piro Collar PC on it, enter the date and the name.

Have questions?

A qualified team of Pirosystem can help in the selection of passive fire protection system and other fire protection solutions.